1
00:00:00,320 --> 00:00:05,100
The last thing we know the engineer said
was that he'd fix it in ten minutes.

2
00:00:05,760 --> 00:00:08,880
He said it over a radio, to a colleague
standing at a pump,

3
00:00:09,160 --> 00:00:10,160
a little after midday.

4
00:00:11,160 --> 00:00:13,240
Ten days later he was dead.

5
00:00:14,200 --> 00:00:16,120
That's the case behind today's episode.

6
00:00:16,800 --> 00:00:20,980
It comes from a safety case written by Dr
Wayne Sundborg, an independent

7
00:00:21,020 --> 00:00:25,060
investigation carried out with the help of
a consulting expert engineer.

8
00:00:25,880 --> 00:00:30,280
Everything in it is anonymised, so we're
working with roles rather than names.

9
00:00:30,840 --> 00:00:36,000
There's the Project Management Team, the
EPC Contractor, the Subcontractor who

10
00:00:36,040 --> 00:00:38,740
employed the engineer, and the Equipment
Supplier.

11
00:00:39,587 --> 00:00:43,847
And because this is a death, I think we
should be plain about how we'll handle it.

12
00:00:44,447 --> 00:00:48,207
We'll stick to what the report
establishes, and where the investigator says

13
00:00:48,287 --> 00:00:50,607
something is an inference, we'll say so
too.

14
00:00:51,847 --> 00:00:52,507
Where is this, then?

15
00:00:52,727 --> 00:00:54,187
What kind of site are we on?

16
00:00:54,810 --> 00:00:57,150
A greenfield independent power plant.

17
00:00:57,710 --> 00:01:02,850
It's an integrated combined cycle gas
turbine plant, so several gas turbines,

18
00:01:03,110 --> 00:01:07,230
steam turbines, heat recovery steam
generators and cooling towers,

19
00:01:07,770 --> 00:01:11,130
fired mainly on natural gas with liquid
fuel as backup.

20
00:01:11,890 --> 00:01:16,050
It's under commissioning, and commercial
operation is expected shortly afterwards.

21
00:01:16,870 --> 00:01:21,810
The main EPC Contractor had handed the
water treatment package to a specialist

22
00:01:21,870 --> 00:01:22,610
Subcontractor.

23
00:01:23,230 --> 00:01:27,570
That firm was responsible for the
demineralisation plant, the Demin plant,

24
00:01:27,970 --> 00:01:31,210
including the electrical panels, the PLC
and the drives.

25
00:01:31,930 --> 00:01:35,610
At the time of the incident the Demin
plant was in the final stage of commissioning,

26
00:01:36,010 --> 00:01:39,610
and most of that Subcontractor's workforce
had already been demobilised.

27
00:01:40,480 --> 00:01:42,780
So a thinned out crew, near the finish
line.

28
00:01:43,420 --> 00:01:44,000
Hold on to that.

29
00:01:45,240 --> 00:01:46,000
Who's the engineer?

30
00:01:46,580 --> 00:01:51,400
A young man in his late twenties, an
Electrical and Instrumentation Engineer

31
00:01:51,740 --> 00:01:53,460
employed by the Subcontractor.

32
00:01:54,320 --> 00:01:58,500
He had a bachelor's degree in technology
and about four years of experience.

33
00:01:59,440 --> 00:02:01,780
The report is careful about his profile.

34
00:02:02,320 --> 00:02:06,400
His record was predominantly PLC and
instrumentation systems,

35
00:02:06,800 --> 00:02:10,240
with no demonstrated hands on electrical
systems competence.

36
00:02:11,119 --> 00:02:15,540
His training was a commissioning safety
induction and permit receiver training.

37
00:02:16,100 --> 00:02:18,800
There's no evidence he'd been trained on
the panel in question.

38
00:02:19,718 --> 00:02:21,998
I'd put that in everyday terms, if I may.

39
00:02:22,458 --> 00:02:26,418
It's someone who can tell you exactly why
a controller is misbehaving,

40
00:02:26,878 --> 00:02:31,938
but who hasn't been shown how to work
safely inside the heavy power equipment behind

41
00:02:31,998 --> 00:02:32,178
it.

42
00:02:32,858 --> 00:02:37,758
That's my interpretation, not the report's
wording, but it seems to be the gap the

43
00:02:37,798 --> 00:02:38,998
report is pointing at.

44
00:02:39,610 --> 00:02:41,390
Yes, I think that's fair.

45
00:02:42,090 --> 00:02:43,130
Now the timeline.

46
00:02:44,090 --> 00:02:48,450
The day before, around nine in the
morning, the Subcontractor obtained a general

47
00:02:48,650 --> 00:02:52,510
permit to work for commissioning of the
motors, valid for several days.

48
00:02:53,430 --> 00:02:56,890
A no load trial run had been reported as
completed successfully,

49
00:02:57,270 --> 00:02:59,170
using local push button operation.

50
00:03:00,230 --> 00:03:04,530
On the incident day, around five to
twelve, the engineer and a colleague were

51
00:03:04,570 --> 00:03:08,210
assigned to carry out the load trial run
of a feed pump stream.

52
00:03:09,030 --> 00:03:12,790
He signed the switchroom entry log, which
was kept by a security guard at the door.

53
00:03:13,690 --> 00:03:19,130
Work began around twelve, during the EPC
lunch break, with no EPC supervision

54
00:03:19,170 --> 00:03:19,590
present.

55
00:03:20,610 --> 00:03:23,330
He was at the switchgear and his colleague
was at the pump.

56
00:03:24,057 --> 00:03:26,737
He starts the pump from the PLC, and it
trips.

57
00:03:27,382 --> 00:03:29,862
The motor tripped after the initial run
up.

58
00:03:30,382 --> 00:03:35,622
In the summary, it's described as failing
to transition from star to delta during

59
00:03:35,722 --> 00:03:36,202
start up.

60
00:03:36,882 --> 00:03:41,082
For anyone who hasn't met it, star delta
starting is a way of being gentle with a

61
00:03:41,122 --> 00:03:41,722
big motor.

62
00:03:42,222 --> 00:03:45,702
It starts in one winding arrangement to
limit the surge of current,

63
00:03:46,142 --> 00:03:48,782
then switches over to the other once it's
up to speed.

64
00:03:49,462 --> 00:03:52,222
So the pump started, and the changeover
didn't happen.

65
00:03:52,742 --> 00:03:54,142
The report doesn't tell us why.

66
00:03:54,802 --> 00:03:59,262
What it does tell us is that post incident
testing found the motor and its cable

67
00:03:59,342 --> 00:04:01,302
healthy, and we'll come back to that.

68
00:04:01,975 --> 00:04:04,395
And that's when he tells his colleague
about the ten minutes.

69
00:04:05,140 --> 00:04:08,120
He radioed that he would rectify the fault
in ten minutes.

70
00:04:09,060 --> 00:04:10,300
Then he went to the panel.

71
00:04:10,940 --> 00:04:15,460
He opened the cable alley, using a
switchgear door key that the report says he held

72
00:04:15,500 --> 00:04:17,040
but wasn't authorised to hold.

73
00:04:17,660 --> 00:04:20,720
He removed the front plate of the
instrumentation and control box,

74
00:04:21,059 --> 00:04:23,580
the I&C box, on the low voltage
switchgear.

75
00:04:24,340 --> 00:04:29,580
The tool he used was a 240 volt test
screwdriver, the maximum rated tool available

76
00:04:29,640 --> 00:04:29,940
to him.

77
00:04:30,560 --> 00:04:35,540
A 240 volt tester screwdriver, on a low
voltage switchboard.

78
00:04:36,600 --> 00:04:40,460
I know we'll get to what that means, but I
just want that detail to sit there for a

79
00:04:40,520 --> 00:04:41,000
second.

80
00:04:41,805 --> 00:04:43,285
It's the detail that stays with you.

81
00:04:44,145 --> 00:04:46,945
Now, here's the point where the report
flags an inference.

82
00:04:47,625 --> 00:04:51,765
It's inferred that the detached metal
cover plate was set down on a cabinet fixing

83
00:04:51,825 --> 00:04:52,745
bar to his right.

84
00:04:53,465 --> 00:04:57,825
It slipped, struck the cables below, and
came to rest on exposed busbars.

85
00:04:58,665 --> 00:05:02,265
A phase to phase arc flash followed, and
he was engulfed in flames.

86
00:05:03,365 --> 00:05:07,005
The security guard at the entrance put the
flames out with carbon dioxide and dry

87
00:05:07,065 --> 00:05:12,005
powder extinguishers, and alerted his
supervisor, who informed the EPC HSE

88
00:05:12,065 --> 00:05:12,725
coordinator.

89
00:05:13,705 --> 00:05:17,365
A site nurse gave first aid, and he was
taken to a local government hospital.

90
00:05:18,540 --> 00:05:21,300
The investigator is open about the limits
of the evidence there,

91
00:05:21,620 --> 00:05:21,920
isn't he?

92
00:05:22,660 --> 00:05:24,560
He is, and it matters.

93
00:05:25,240 --> 00:05:30,320
The witness statements were taken by the
EPC HSE team rather than an independent

94
00:05:30,380 --> 00:05:30,800
party.

95
00:05:31,600 --> 00:05:35,200
By the time of the independent
investigation, none of the witnesses remained

96
00:05:35,260 --> 00:05:36,420
available on the project.

97
00:05:37,260 --> 00:05:40,120
Documentary copies couldn't be re verified
at source.

98
00:05:40,760 --> 00:05:43,580
And the precise way the cover plate
reached the busbars is,

99
00:05:43,980 --> 00:05:47,620
in his words, an inference based on
experience of similar events.

100
00:05:48,300 --> 00:05:52,880
So we have a firm physical outcome, and
one step in the middle that's reasoned

101
00:05:52,960 --> 00:05:53,820
rather than witnessed.

102
00:05:54,658 --> 00:05:55,598
The injuries, then.

103
00:05:56,138 --> 00:05:58,078
I'd rather say them once and plainly.

104
00:05:58,847 --> 00:06:01,907
Burns to more than ninety per cent of his
body surface.

105
00:06:02,507 --> 00:06:06,967
About sixty per cent was partial
thickness, and more than thirty per cent was full

106
00:06:07,027 --> 00:06:07,447
thickness.

107
00:06:08,127 --> 00:06:12,687
There was also third degree burning of the
airways, lung damage from inhaling flame,

108
00:06:13,127 --> 00:06:16,507
and acute trauma to the larynx, trachea
and bronchi.

109
00:06:17,127 --> 00:06:21,807
The investigator says that pattern is
consistent with direct engulfment in an arc

110
00:06:21,867 --> 00:06:25,827
flash fireball at close range, without arc
rated protection.

111
00:06:26,687 --> 00:06:31,127
The inhalation burns show he was within
the immediate plasma and flame envelope.

112
00:06:31,647 --> 00:06:36,207
And he states that appropriate arc flash
PPE and an enforced minimum approach

113
00:06:36,267 --> 00:06:39,027
boundary would have materially altered the
outcome.

114
00:06:39,847 --> 00:06:41,787
He died ten days after the injury.

115
00:06:42,708 --> 00:06:46,388
Let's start where an investigator has to
start, which is whether something

116
00:06:46,448 --> 00:06:48,048
electrical went wrong first.

117
00:06:48,868 --> 00:06:51,808
A pump fails to change over, an engineer
goes to look.

118
00:06:52,388 --> 00:06:56,168
It would be easy to assume the equipment
failed and the fireball followed.

119
00:06:56,808 --> 00:06:58,508
The report closes that door.

120
00:06:59,308 --> 00:07:02,928
After the incident, the motor and its
connecting cable were tested.

121
00:07:03,408 --> 00:07:06,748
There was no phase to ground fault, and
both were found healthy.

122
00:07:07,668 --> 00:07:11,688
On the facts collected, no electrical
fault was present that would have caused the

123
00:07:11,768 --> 00:07:12,288
arc flash.

124
00:07:13,048 --> 00:07:17,268
On the engineering assessment, an
electrical fault is a highly unlikely cause.

125
00:07:17,968 --> 00:07:20,228
The initiating mechanism was mechanical.

126
00:07:20,748 --> 00:07:23,228
A metal plate touched live busbars.

127
00:07:24,038 --> 00:07:25,418
Which is almost banal.

128
00:07:26,038 --> 00:07:27,738
A plate slides off a bar.

129
00:07:28,498 --> 00:07:33,598
It's the kind of thing that happens in any
workshop, a panel or a lid set down where

130
00:07:33,618 --> 00:07:34,258
it shouldn't be.

131
00:07:34,898 --> 00:07:38,638
The question must be why that ordinary
slip could be fatal.

132
00:07:39,298 --> 00:07:42,038
Right, and the answer is in the build of
the panel.

133
00:07:42,618 --> 00:07:45,018
This is where the consulting engineer's
work comes in.

134
00:07:46,058 --> 00:07:50,718
The switchgear was supplied by a control
technology firm and built by a third party

135
00:07:50,798 --> 00:07:53,178
panel integrator from bought out
components.

136
00:07:53,858 --> 00:07:57,678
The cabinets arrived as flat pack units
and were assembled on site.

137
00:07:58,458 --> 00:08:03,438
The report calls that on site assembly a
critical point where a construction defect

138
00:08:03,478 --> 00:08:05,238
was introduced and never caught.

139
00:08:05,910 --> 00:08:06,710
Flat pack.

140
00:08:07,250 --> 00:08:08,990
I keep picturing wardrobes.

141
00:08:09,723 --> 00:08:14,283
It's not a bad picture, to be fair, as
long as the wardrobe has a few thousand amps

142
00:08:14,323 --> 00:08:15,103
behind the doors.

143
00:08:15,963 --> 00:08:20,003
Think about the last time you built one
and found a panel on upside down at the end.

144
00:08:20,683 --> 00:08:21,563
You can usually see it.

145
00:08:22,343 --> 00:08:23,083
Nobody dies.

146
00:08:23,943 --> 00:08:25,523
Here, nobody looked.

147
00:08:26,418 --> 00:08:28,258
What exactly did they find wrong?

148
00:08:29,080 --> 00:08:29,520
A list.

149
00:08:30,380 --> 00:08:33,900
Busbar to panel clearances differed on the
two sides of the panel.

150
00:08:34,660 --> 00:08:39,040
Control and instrumentation cables were
running directly over the busbars.

151
00:08:39,880 --> 00:08:41,700
Cable gland holes were not sealed.

152
00:08:42,400 --> 00:08:46,020
Loose hardware was resting on the busbars
and inside the panels.

153
00:08:46,720 --> 00:08:51,680
And the headline defect: the partition
cover of one vertical section was installed

154
00:08:51,760 --> 00:08:55,380
incorrectly, exposing the live busbar in
the cable alley.

155
00:08:56,282 --> 00:08:57,602
Explain that one properly.

156
00:08:58,082 --> 00:09:00,942
What does installed incorrectly mean,
physically?

157
00:09:01,753 --> 00:09:05,533
The internal wall inside the cabinet is
meant to separate the cable alley,

158
00:09:05,753 --> 00:09:08,333
where people work on cables, from the
busbars.

159
00:09:09,113 --> 00:09:13,233
The report says it should be fixed from
bottom to top, leaving a gap at the top,

160
00:09:13,393 --> 00:09:14,013
not the bottom.

161
00:09:14,693 --> 00:09:17,613
It was fitted inverted, so the opening was
in the wrong place,

162
00:09:18,013 --> 00:09:20,593
and the live busbars were exposed in the
cable alley.

163
00:09:21,473 --> 00:09:23,953
It's a bit like fitting the guard on a saw
the wrong way up,

164
00:09:24,193 --> 00:09:26,653
so the opening for the blade ends up where
your hand goes.

165
00:09:27,513 --> 00:09:30,793
That's my analogy, not the report's, but
the logic is the same.

166
00:09:31,573 --> 00:09:34,973
The thing that was supposed to keep you
away from the live parts had been turned

167
00:09:35,033 --> 00:09:36,213
into the way to reach them.

168
00:09:36,800 --> 00:09:39,660
And the busbars themselves weren't
protected either.

169
00:09:40,237 --> 00:09:40,437
No.

170
00:09:41,077 --> 00:09:45,377
The busbars and busbar droppers were bare,
not sleeved, even though the

171
00:09:45,457 --> 00:09:47,317
specification required sleeving.

172
00:09:48,177 --> 00:09:53,257
The standard engaged is IEC 61439 part 1,
clause

173
00:09:53,497 --> 00:09:55,217
8.4.2.2.

174
00:09:55,977 --> 00:10:00,017
In substance, it requires hazardous live
parts to be completely covered with

175
00:10:00,057 --> 00:10:04,077
insulation that can only be removed by
destroying it, or by using a tool.

176
00:10:04,957 --> 00:10:08,017
The insulation has to be able to durably
withstand the mechanical,

177
00:10:08,357 --> 00:10:11,097
electrical and thermal stresses it will
see in service.

178
00:10:11,777 --> 00:10:14,777
The switchgear was found in a state not
fully complying with that.

179
00:10:15,647 --> 00:10:16,947
So there are two layers there.

180
00:10:17,367 --> 00:10:21,047
Bare conductors, and then a partition that
should have been a second line of

181
00:10:21,087 --> 00:10:23,027
defence, fitted so it wasn't.

182
00:10:23,690 --> 00:10:24,690
Plus a third.

183
00:10:25,430 --> 00:10:27,970
The doors were secured with hinges and
latches.

184
00:10:28,510 --> 00:10:32,510
The report says access to bus compartments
should require correct tools,

185
00:10:32,790 --> 00:10:35,970
and shields should be provided, and
neither condition was met.

186
00:10:36,770 --> 00:10:41,070
Once the doors were opened, the panel
reverted to what's called IP00,

187
00:10:41,370 --> 00:10:44,490
which means no protection against contact
with live parts.

188
00:10:45,070 --> 00:10:49,310
So opening a latch took him from a closed
cabinet to an open one with nothing in the

189
00:10:49,350 --> 00:10:49,590
way.

190
00:10:50,480 --> 00:10:54,000
Did the report look at whether the
specification itself was weak?

191
00:10:54,807 --> 00:10:55,387
Only a little.

192
00:10:55,887 --> 00:10:59,847
Comparing the two switchgears in the same
room indicated the specification was

193
00:10:59,907 --> 00:11:01,027
generic in nature.

194
00:11:01,467 --> 00:11:04,547
But the specification wasn't evaluated as
part of the investigation,

195
00:11:04,927 --> 00:11:08,747
and the investigator expresses no opinion
on its adequacy beyond noting that

196
00:11:08,787 --> 00:11:09,267
character.

197
00:11:10,027 --> 00:11:13,827
There's also one thing the engineer
couldn't establish, which is the significance of

198
00:11:13,847 --> 00:11:16,847
metallic cable termination boxes in the
cable alley.

199
00:11:17,527 --> 00:11:20,147
I like that the report says that rather
than papering over it.

200
00:11:20,715 --> 00:11:24,915
There's a thread here that connects to the
idea we keep coming back to in this

201
00:11:24,975 --> 00:11:25,455
series.

202
00:11:26,255 --> 00:11:27,755
The visible event is small.

203
00:11:28,455 --> 00:11:30,675
A man took a plate off and put it down.

204
00:11:31,515 --> 00:11:36,195
If you stop your investigation at that
moment, you'd write down human error and go

205
00:11:36,235 --> 00:11:36,455
home.

206
00:11:37,265 --> 00:11:41,365
Which is the idea from the accident models
episode, that the human act is where the

207
00:11:41,405 --> 00:11:43,905
investigation starts, not where it ends.

208
00:11:44,605 --> 00:11:46,445
Here the investigator makes it concrete.

209
00:11:46,985 --> 00:11:50,965
The panel was in a condition where a
mundane slip could produce a fireball.

210
00:11:51,625 --> 00:11:54,825
That condition was built in before he was
ever assigned the job.

211
00:11:55,385 --> 00:11:58,285
The question then becomes who should have
noticed, and when.

212
00:11:59,065 --> 00:12:02,725
Who should have noticed is the part I find
hardest to get my head around,

213
00:12:03,165 --> 00:12:04,405
so let's do it carefully.

214
00:12:05,025 --> 00:12:09,865
Because there was supposed to be a system
of inspection between a flat pack cabinet

215
00:12:09,925 --> 00:12:12,605
arriving and an engineer standing in front
of it.

216
00:12:13,215 --> 00:12:17,955
There was, and the report counts about
nine inspection hold points between

217
00:12:17,995 --> 00:12:19,775
construction and turnover.

218
00:12:20,535 --> 00:12:22,915
Let me read them out, because the length
of the list is the point.

219
00:12:23,815 --> 00:12:27,715
A quality inspection of the cabinet
construction by the Subcontractor.

220
00:12:28,475 --> 00:12:30,795
The same again by the EPC Contractor.

221
00:12:31,555 --> 00:12:33,755
The same again by the Project Management
Team.

222
00:12:34,695 --> 00:12:38,895
Then a quality inspection of the
installation of the electrical components.

223
00:12:39,675 --> 00:12:41,655
A pre energisation inspection.

224
00:12:42,295 --> 00:12:43,995
An energisation inspection.

225
00:12:44,875 --> 00:12:46,735
A pre commissioning inspection.

226
00:12:47,395 --> 00:12:48,755
A commissioning inspection.

227
00:12:49,415 --> 00:12:51,575
And a turnover package inspection.

228
00:12:52,478 --> 00:12:53,398
Nine chances.

229
00:12:54,182 --> 00:12:58,302
And the finding is that no quality checks
were undertaken during construction.

230
00:12:59,002 --> 00:13:04,642
The EPC Contractor and the Project
Management Team each signed off QA/QC acceptance

231
00:13:04,702 --> 00:13:05,782
with no inspection.

232
00:13:06,522 --> 00:13:11,702
The PMT quality manager said in interview
that he rarely inspected physically and

233
00:13:11,742 --> 00:13:15,042
relied on information provided by the EPC
Contractor.

234
00:13:15,782 --> 00:13:19,142
The turnover package manager admitted he
never visited site,

235
00:13:19,522 --> 00:13:23,742
that his sign off was a desktop exercise,
and that he generally read only the cover

236
00:13:23,782 --> 00:13:24,982
sheet before stamping.

237
00:13:25,642 --> 00:13:27,102
He subsequently resigned.

238
00:13:27,685 --> 00:13:28,745
Only the cover sheet.

239
00:13:30,185 --> 00:13:34,865
Let me push on this, because I can imagine
someone saying that's one person being

240
00:13:34,925 --> 00:13:35,405
lazy.

241
00:13:35,945 --> 00:13:37,265
Is the report treating it that way?

242
00:13:38,033 --> 00:13:40,173
No, and I think that's the sharper
reading.

243
00:13:40,673 --> 00:13:41,633
Look at how it's arranged.

244
00:13:42,113 --> 00:13:45,813
The PMT quality manager relied on the EPC
Contractor's information.

245
00:13:46,393 --> 00:13:48,693
The EPC Contractor signed off without
inspecting.

246
00:13:49,333 --> 00:13:52,633
The turnover manager relied on a package
that had been signed off by the layers

247
00:13:52,693 --> 00:13:53,173
below.

248
00:13:54,093 --> 00:13:57,333
Each signature leaned on the one before
it, and the first one in the chain was

249
00:13:57,393 --> 00:13:57,693
empty.

250
00:13:58,293 --> 00:14:00,973
It's like a row of people each checking
the ticket of the person in front,

251
00:14:01,393 --> 00:14:02,633
and nobody ever looks at the train.

252
00:14:03,410 --> 00:14:06,210
And the report is clear about what an
inspection would have done.

253
00:14:06,800 --> 00:14:09,580
It calls it a critical causal link.

254
00:14:10,280 --> 00:14:14,600
Had any one of the quality, pre
energisation, energisation,

255
00:14:14,920 --> 00:14:20,080
commissioning or turnover inspections been
carried out, the incorrectly constructed

256
00:14:20,140 --> 00:14:23,300
internal cabinet wall would have been
identified early.

257
00:14:23,940 --> 00:14:24,860
And it goes further.

258
00:14:25,280 --> 00:14:30,400
A single working inspection at any of nine
hold points would most likely have caught

259
00:14:30,440 --> 00:14:32,540
the defect that killed the engineer.

260
00:14:33,337 --> 00:14:36,497
That phrase, most likely, is doing honest
work.

261
00:14:36,957 --> 00:14:38,177
It's not saying certainly.

262
00:14:38,818 --> 00:14:40,578
Right, it's a considered judgement.

263
00:14:41,458 --> 00:14:44,318
Now, the second paper control, the permit
to work.

264
00:14:45,078 --> 00:14:47,638
The engineer's permit was obtained the day
before.

265
00:14:48,238 --> 00:14:50,038
It was for mechanical works only.

266
00:14:50,598 --> 00:14:54,158
The activities specified did not state
work on a live system,

267
00:14:54,598 --> 00:14:57,258
and the water treatment switchgear was
nowhere mentioned.

268
00:14:57,858 --> 00:15:01,978
It wasn't a permit for the switchroom, and
it wasn't a permit for electrical work.

269
00:15:02,855 --> 00:15:03,575
And the duration?

270
00:15:04,145 --> 00:15:09,325
The permit was dated for seven days,
against an eight to twelve hour plan limit.

271
00:15:09,825 --> 00:15:14,105
So it was broad in time and narrow in
scope, which is the wrong way round.

272
00:15:14,965 --> 00:15:17,205
And the investigator's conclusion is
blunt.

273
00:15:17,765 --> 00:15:22,445
The work that led to the death was carried
out without a valid permit to work for

274
00:15:22,485 --> 00:15:24,285
the activity actually undertaken.

275
00:15:24,845 --> 00:15:29,285
He also notes the deceased wasn't
authorised to work on a live electrical system

276
00:15:29,345 --> 00:15:30,705
without a valid permit.

277
00:15:31,738 --> 00:15:33,438
Was anyone checking permits?

278
00:15:34,335 --> 00:15:39,555
No PTW audits were carried out by either
the EPC Contractor or the Project

279
00:15:39,595 --> 00:15:40,335
Management Team.

280
00:15:41,195 --> 00:15:44,995
There was no task specific risk assessment
for the activity that resulted in the

281
00:15:45,055 --> 00:15:45,335
death.

282
00:15:45,975 --> 00:15:49,795
The commissioning risk assessments were
generic and effectively identical to the

283
00:15:49,855 --> 00:15:51,735
generic construction risk assessment.

284
00:15:52,655 --> 00:15:55,715
Method statements were poor, with
essential information missing.

285
00:15:56,775 --> 00:16:01,255
Commissioning areas weren't adequately
identified, and access control wasn't

286
00:16:01,315 --> 00:16:02,295
effectively managed.

287
00:16:03,235 --> 00:16:04,095
Then there's the key.

288
00:16:04,855 --> 00:16:08,695
An uncontrolled switchgear panel door key
was held by the deceased,

289
00:16:09,115 --> 00:16:10,575
who wasn't authorised to hold it.

290
00:16:11,193 --> 00:16:13,213
So think about what he was walking
through.

291
00:16:13,833 --> 00:16:15,693
The permit didn't mention the room.

292
00:16:16,213 --> 00:16:17,833
The key opened the door anyway.

293
00:16:18,453 --> 00:16:21,393
The risk assessment was a copy of a
construction one.

294
00:16:21,913 --> 00:16:23,753
The inspections had been stamped.

295
00:16:25,213 --> 00:16:29,953
At every point where something could have
said stop, the paper said carry on,

296
00:16:30,493 --> 00:16:31,253
or said nothing.

297
00:16:32,125 --> 00:16:34,325
That's close to how the investigator
frames it.

298
00:16:35,045 --> 00:16:39,425
His method treats each of these as a
barrier, a defence that should have arrested

299
00:16:39,465 --> 00:16:43,905
the sequence, and his finding is that
every one had already failed before the

300
00:16:43,945 --> 00:16:45,165
engineer touched the panel.

301
00:16:46,305 --> 00:16:48,185
He doesn't say the engineer was blameless.

302
00:16:48,665 --> 00:16:52,105
He says the engineer arrived at the end of
a chain where the failures had been

303
00:16:52,165 --> 00:16:54,205
accumulating without anyone noticing.

304
00:16:54,922 --> 00:16:56,342
And one more piece of timing.

305
00:16:56,902 --> 00:16:58,542
The work happened at lunchtime.

306
00:16:59,347 --> 00:16:59,827
It did.

307
00:17:01,127 --> 00:17:06,407
Work began around twelve, during the EPC
lunch break, with no EPC supervision

308
00:17:06,507 --> 00:17:06,927
present.

309
00:17:07,987 --> 00:17:11,787
The report says that suggests the work
proceeded without supervision by the

310
00:17:11,827 --> 00:17:13,687
principal EPC Contractor.

311
00:17:14,427 --> 00:17:18,847
And later, in the corrective actions, one
of the recommendations is to prohibit work

312
00:17:18,907 --> 00:17:23,587
during the EPC lunch window, which tells
you how the investigator reads that gap.

313
00:17:24,388 --> 00:17:28,028
Let's talk about what he had in his hands
and on his body.

314
00:17:28,588 --> 00:17:31,168
Because the tool detail is the one I can't
shake.

315
00:17:32,023 --> 00:17:36,943
The report calls a 240 volt line tester, a
tester screwdriver,

316
00:17:37,463 --> 00:17:40,543
neither acceptable nor good practice in
industry for this purpose.

317
00:17:41,343 --> 00:17:45,083
It says it provides no protection against
the energy present in the switchgear.

318
00:17:45,923 --> 00:17:49,463
To be clear, the engineer wasn't being
reckless with a better tool in the cupboard.

319
00:17:49,923 --> 00:17:53,823
The report describes it as the maximum
rated tool available to him.

320
00:17:54,587 --> 00:17:57,347
So the site had no tool he could have used
correctly.

321
00:17:57,742 --> 00:18:01,622
That's the implication, though I'd stay
with the report's wording,

322
00:18:02,042 --> 00:18:05,462
which is that it was the maximum rated
tool available to him.

323
00:18:06,482 --> 00:18:08,822
And the protective equipment tells the
same story.

324
00:18:09,482 --> 00:18:15,162
The deceased wasn't wearing suitable PPE,
and the general PPE was of poor quality

325
00:18:15,242 --> 00:18:16,202
and substandard.

326
00:18:17,122 --> 00:18:22,242
There was no evidence that the EPC
Contractor or the Subcontractor held arc flash

327
00:18:22,322 --> 00:18:23,922
suits in their PPE stock.

328
00:18:24,962 --> 00:18:28,142
No evidence of insulating gloves in either
party's stock.

329
00:18:29,002 --> 00:18:33,922
Rubber matting was present, but it didn't
meet IEC and EN 61111,

330
00:18:34,382 --> 00:18:36,702
and it came from an unverified
manufacturer.

331
00:18:37,410 --> 00:18:42,470
Matting that exists but doesn't meet the
standard is oddly worse than no matting.

332
00:18:43,110 --> 00:18:44,470
It looks like protection.

333
00:18:45,132 --> 00:18:50,152
That's a good observation, and it's my
reading too, though it's an interpretation.

334
00:18:51,032 --> 00:18:53,012
The same goes for the emergency response.

335
00:18:53,652 --> 00:18:58,112
The contributing factors list notes that
only fire extinguishers were available at

336
00:18:58,132 --> 00:18:58,592
the scene.

337
00:18:59,652 --> 00:19:02,412
And it was the security guard at the door
who used them.

338
00:19:03,112 --> 00:19:05,952
He wasn't a medic and wasn't part of the
commissioning team.

339
00:19:06,492 --> 00:19:09,252
He was the person who happened to be there
with an extinguisher.

340
00:19:09,850 --> 00:19:11,150
Now, on competence.

341
00:19:11,750 --> 00:19:16,510
The Subcontractor designated him for Demin
plant commissioning across both

342
00:19:16,570 --> 00:19:18,750
instrumentation and electrical systems.

343
00:19:19,423 --> 00:19:23,923
Yes, and the review of his record showed
work predominantly on PLC and

344
00:19:23,983 --> 00:19:28,123
instrumentation, with no suitable hands on
electrical experience evident.

345
00:19:28,803 --> 00:19:31,403
There was no evidence he'd been trained on
the panel concerned,

346
00:19:31,823 --> 00:19:34,043
or on the other panels he was made
responsible for.

347
00:19:34,823 --> 00:19:38,383
The report's table of failures by
accountable party puts it directly.

348
00:19:38,943 --> 00:19:44,083
The Subcontractor tasked an I&C engineer
with electrical work he was neither trained

349
00:19:44,143 --> 00:19:45,243
nor authorised for.

350
00:19:46,063 --> 00:19:48,903
There was also no evidence of a toolbox
talk by the Subcontractor,

351
00:19:49,443 --> 00:19:53,523
and the commissioning safety induction was
poor, delivered by a safety officer with

352
00:19:53,583 --> 00:19:55,423
no commissioning safety experience.

353
00:19:56,192 --> 00:19:58,232
So who was meant to be watching all this?

354
00:19:58,512 --> 00:19:59,412
Where were the managers?

355
00:20:00,112 --> 00:20:03,952
This is the section that goes into what
the investigator calls a pervasive

356
00:20:04,172 --> 00:20:08,992
production over safety culture and a
pattern of absentee oversight.

357
00:20:09,852 --> 00:20:13,152
The PMT offices were about a hundred
metres from the site.

358
00:20:13,912 --> 00:20:18,292
The team was described as complacent and
not visible on site.

359
00:20:19,032 --> 00:20:19,912
A hundred metres.

360
00:20:20,332 --> 00:20:23,432
That's a short walk, the length of a
football pitch, give or take.

361
00:20:24,110 --> 00:20:25,810
And the EPC safety people?

362
00:20:26,517 --> 00:20:31,437
The EPC HSE manager admitted visiting site
only a few times per week,

363
00:20:31,957 --> 00:20:37,417
generally outside active periods, citing
workload and language barriers between the

364
00:20:37,457 --> 00:20:38,357
workforce groups.

365
00:20:39,257 --> 00:20:43,917
The report says that language barrier left
Subcontractors effectively unsupervised.

366
00:20:44,797 --> 00:20:50,557
And the EPC deputy HSE manager also served
as deputy construction manager.

367
00:20:51,237 --> 00:20:55,677
The investigator calls that a conflict of
role, and I'd put it plainly.

368
00:20:56,237 --> 00:21:00,077
The person who's supposed to be the check
on the schedule is also the person

369
00:21:00,117 --> 00:21:01,537
responsible for delivering it.

370
00:21:02,112 --> 00:21:04,772
That one bothers me more than the absentee
offices.

371
00:21:05,452 --> 00:21:07,092
Because absence is a lapse.

372
00:21:07,692 --> 00:21:09,932
A conflict of role is a design choice.

373
00:21:10,432 --> 00:21:12,252
Someone built that organisation chart.

374
00:21:13,330 --> 00:21:17,330
Fair point, and the report does list it
among structural findings.

375
00:21:18,390 --> 00:21:19,549
There's also working time.

376
00:21:20,229 --> 00:21:23,530
Operatives routinely worked in excess of
sixteen hours a day.

377
00:21:24,590 --> 00:21:25,550
I want to be careful here.

378
00:21:25,970 --> 00:21:28,150
The report says that about operatives
generally.

379
00:21:28,730 --> 00:21:32,450
It doesn't say how long this particular
engineer had been working that day or that

380
00:21:32,510 --> 00:21:32,790
week.

381
00:21:33,250 --> 00:21:35,910
So I wouldn't claim fatigue played a part
in his decision.

382
00:21:36,630 --> 00:21:40,810
What I can say is that the project's pace
was set so that long days were routine,

383
00:21:41,370 --> 00:21:43,150
and that's a sign of where the priorities
sat.

384
00:21:44,103 --> 00:21:45,943
And the interviews with senior people.

385
00:21:46,610 --> 00:21:50,950
The investigator describes a complacent
leadership tone from the top,

386
00:21:51,510 --> 00:21:52,870
and he gives two illustrations.

387
00:21:53,750 --> 00:21:57,150
First, one senior manager recounted that,
as an apprentice,

388
00:21:57,630 --> 00:22:02,270
the practice had been to wet a finger and
briefly touch a cable to check whether it

389
00:22:02,310 --> 00:22:03,150
was energised.

390
00:22:03,790 --> 00:22:07,710
The report notes the original statement
was unusable for legal reasons,

391
00:22:08,110 --> 00:22:11,390
so this is offered as an illustration of
the attitude he encountered.

392
00:22:12,450 --> 00:22:16,910
Second, a construction manager admitted he
hadn't wanted to be on the project and

393
00:22:16,970 --> 00:22:18,030
rarely visited site.

394
00:22:18,877 --> 00:22:23,637
The wet finger story is almost a joke,
until you remember what happened here.

395
00:22:24,317 --> 00:22:28,357
A man trying to find out if something is
live, using a tool that can't tell him

396
00:22:28,437 --> 00:22:30,777
anything useful about the energy in front
of him.

397
00:22:31,465 --> 00:22:34,885
I'd be careful about drawing a straight
line, because the report doesn't.

398
00:22:35,605 --> 00:22:40,365
What it says is that such attitudes are
indicative of the cultural conditions in

399
00:22:40,405 --> 00:22:42,165
which this fatality became possible.

400
00:22:42,845 --> 00:22:47,265
It's a statement about climate, not a
claim about what any one person thought that

401
00:22:47,305 --> 00:22:47,485
day.

402
00:22:48,070 --> 00:22:52,270
Let's get into how Dr Sundborg actually
reasoned his way to a cause.

403
00:22:52,690 --> 00:22:54,470
He doesn't just list defects.

404
00:22:55,163 --> 00:22:56,743
He combines three methods.

405
00:22:57,123 --> 00:23:01,463
A bow tie sequencing of the event, a Five
Whys drill down to root level,

406
00:23:01,943 --> 00:23:06,123
and a cross check against a fishbone
analysis, the man, machine,

407
00:23:06,223 --> 00:23:09,963
method and management headings, so no
causal branch was overlooked.

408
00:23:10,583 --> 00:23:12,063
The bow tie runs like this.

409
00:23:12,683 --> 00:23:17,003
The hazard is energised, unsleeved busbars
exposed in the cable alley.

410
00:23:17,563 --> 00:23:22,123
The task is live fault finding with a 240
volt test screwdriver.

411
00:23:22,783 --> 00:23:26,583
The trigger is the metal cover plate
slipping onto the exposed busbars.

412
00:23:27,103 --> 00:23:29,483
The event is a phase to phase arc flash.

413
00:23:30,023 --> 00:23:34,403
The outcome is burns to over ninety per
cent of the body and death after ten days.

414
00:23:35,233 --> 00:23:38,433
And every barrier between those boxes was
already gone.

415
00:23:39,108 --> 00:23:39,868
That's the claim.

416
00:23:40,548 --> 00:23:42,028
Now the Five Whys.

417
00:23:42,828 --> 00:23:44,328
Why did the engineer die?

418
00:23:45,108 --> 00:23:49,568
An arc flash engulfed him in flames,
causing the burns and inhalation injury.

419
00:23:50,488 --> 00:23:51,468
Why did it occur?

420
00:23:52,088 --> 00:23:55,808
A metal cover plate slipped onto live
exposed busbars.

421
00:23:56,708 --> 00:23:58,428
Why were they exposed and reachable?

422
00:23:59,108 --> 00:24:02,868
The partition was fitted incorrectly, the
busbars were unsleeved,

423
00:24:03,228 --> 00:24:05,868
and he was doing live work with the doors
open.

424
00:24:06,728 --> 00:24:09,988
Why was the defect never caught, and live
work allowed?

425
00:24:10,908 --> 00:24:16,248
Nine inspections were signed off without
inspection, and no valid electrical permit,

426
00:24:16,608 --> 00:24:19,368
risk assessment or supervision controlled
the task.

427
00:24:20,048 --> 00:24:23,948
And the fifth why, why did the management
system permit all that?

428
00:24:24,668 --> 00:24:30,648
A production over safety culture, with
absentee oversight by the PMT and EPC teams

429
00:24:30,728 --> 00:24:32,268
and unenforced procedures.

430
00:24:32,868 --> 00:24:35,328
That's what he names the true root cause.

431
00:24:36,363 --> 00:24:37,643
Here's where I want to push, though.

432
00:24:38,243 --> 00:24:41,643
Whatever the culture, he still opened a
live panel.

433
00:24:42,083 --> 00:24:43,143
He took the plate off.

434
00:24:43,523 --> 00:24:44,383
He made a choice.

435
00:24:45,063 --> 00:24:47,343
Isn't there a point where the individual
owns that?

436
00:24:48,078 --> 00:24:49,498
The report doesn't dodge it.

437
00:24:50,198 --> 00:24:55,518
In the table of accountable parties, the
individual is listed as having undertaken

438
00:24:55,618 --> 00:25:01,178
live fault finding without authority,
valid permit, correct tools or PPE.

439
00:25:02,238 --> 00:25:05,978
The investigator calls the immediate
unsafe act the deceased's.

440
00:25:06,758 --> 00:25:08,978
But he adds the qualifier that matters.

441
00:25:09,718 --> 00:25:12,578
Individual culpability is heavily
mitigated.

442
00:25:13,398 --> 00:25:16,958
He was a young engineer, assigned a task
outside his competence,

443
00:25:17,238 --> 00:25:21,398
without authority, supervision, correct
tools or protective equipment,

444
00:25:21,778 --> 00:25:26,038
on a defective asset that should never
have presented exposed live parts.

445
00:25:26,958 --> 00:25:31,518
The dominant failures lie with the
management, quality and supply systems above him.

446
00:25:32,527 --> 00:25:36,007
I think that's right, and I'd like to say
why in my own terms.

447
00:25:36,767 --> 00:25:39,187
Ask what a different person would have
done.

448
00:25:39,727 --> 00:25:43,247
If you replaced him with another engineer
from the same Subcontractor,

449
00:25:43,647 --> 00:25:47,927
with the same record, the same key, the
same tool and the same instruction,

450
00:25:48,446 --> 00:25:50,327
the same panel would have been waiting.

451
00:25:50,947 --> 00:25:55,407
The unsafe act can be removed from the
story and the hazard is still there.

452
00:25:56,303 --> 00:25:59,423
That's the heart of the thesis we've been
working with through this series.

453
00:26:00,303 --> 00:26:04,523
Human error is the starting point of the
investigation rather than the conclusion.

454
00:26:05,423 --> 00:26:07,723
The report states root cause in two parts.

455
00:26:08,463 --> 00:26:12,303
The unsafe condition was live busbars left
exposed in the cable alley,

456
00:26:12,743 --> 00:26:16,743
with the internal partition fitted
inverted and the busbars unsleeved,

457
00:26:17,163 --> 00:26:22,923
contrary to IEC 61439 part 1 clause
8.4.2.2.

458
00:26:24,243 --> 00:26:29,483
The unsafe act was live fault finding by
an unauthorised, instrumentation biased

459
00:26:29,523 --> 00:26:35,283
engineer, under no permit for electrical
work, with a 240 volt test screwdriver and

460
00:26:35,343 --> 00:26:36,583
no arc PPE.

461
00:26:37,503 --> 00:26:38,843
And then the line that links them.

462
00:26:39,623 --> 00:26:44,483
Why it reached him: nine QA/QC hold points
signed off without inspection,

463
00:26:45,103 --> 00:26:49,923
no task risk assessment, no supervision,
no lockout tagout control.

464
00:26:50,692 --> 00:26:53,792
The report also divides the failures by
who was accountable.

465
00:26:54,443 --> 00:26:54,803
It does.

466
00:26:55,583 --> 00:27:01,623
The Project Management Team: absentee
oversight, QA/QC and turnover packages signed

467
00:27:01,663 --> 00:27:06,383
as desktop exercises, no permit audits, a
complacent leadership tone.

468
00:27:07,243 --> 00:27:12,803
The EPC Management Team: permit system not
enforced, the HSE manager on site a few

469
00:27:12,863 --> 00:27:17,463
times a week, sub contractors effectively
unsupervised, a production culture.

470
00:27:18,283 --> 00:27:23,163
The Subcontractor: incorrect panel build
and installation, no toolbox talk,

471
00:27:23,683 --> 00:27:26,223
an I&C engineer tasked with electrical
work.

472
00:27:27,143 --> 00:27:32,723
The Equipment Supplier: switchgear
delivered not complying with IEC 61439 part 1,

473
00:27:33,143 --> 00:27:38,703
with unsleeved busbars, IP00 when open and
no bus compartment shields.

474
00:27:39,443 --> 00:27:43,903
And last, the individual, enabled and
directed by all the failures above.

475
00:27:44,833 --> 00:27:48,013
Five parties, and every one of them could
have stopped it.

476
00:27:48,513 --> 00:27:49,513
That's what stays with me.

477
00:27:50,093 --> 00:27:51,173
It isn't one villain.

478
00:27:51,713 --> 00:27:54,593
It's a lot of reasonable looking gaps
lining up.

479
00:27:55,358 --> 00:27:57,798
The contributing factors section says
exactly that.

480
00:27:58,478 --> 00:28:00,738
Each factor removed or weakened a defence.

481
00:28:01,358 --> 00:28:04,738
No single factor caused the death; their
accumulation did.

482
00:28:05,438 --> 00:28:09,178
And the conclusion goes on to say the arc
flash was simply the moment at which those

483
00:28:09,218 --> 00:28:11,218
accumulated failures met a person.

484
00:28:17,503 --> 00:28:19,583
What does the report want done about it?

485
00:28:20,263 --> 00:28:22,243
This is the closing the loop part.

486
00:28:22,963 --> 00:28:25,583
An investigation that ends at blame isn't
much use.

487
00:28:26,360 --> 00:28:30,060
The action plan is in three horizons,
addressed jointly to the PMT,

488
00:28:30,620 --> 00:28:32,960
the EPC Management Team and the
Subcontractor.

489
00:28:33,920 --> 00:28:37,320
In the first twenty four to seventy two
hours: stop all live work,

490
00:28:37,760 --> 00:28:40,680
isolate the water treatment switchgear and
apply lockout tagout,

491
00:28:41,320 --> 00:28:44,800
quarantine the panel and commission an
independent arc flash hazard survey,

492
00:28:45,360 --> 00:28:48,340
suspend all permits and recall every
uncontrolled key.

493
00:28:49,080 --> 00:28:51,040
The aim is to make the asset and the site
safe.

494
00:28:51,950 --> 00:28:52,870
And then the repairs.

495
00:28:53,367 --> 00:28:58,047
Two to six weeks, owned by the
Subcontractor and the EPC Contractor.

496
00:28:58,827 --> 00:29:03,027
Reissue the permit system and prohibit
work during the EPC lunch window.

497
00:29:03,867 --> 00:29:10,627
Sleeve the busbars, refit the partition
and verify the asset against IEC 61439

498
00:29:10,687 --> 00:29:11,207
part 1.

499
00:29:12,247 --> 00:29:17,347
Re verify the competence of all
commissioning personnel, and procure arc flash PPE

500
00:29:17,427 --> 00:29:20,607
and matting to IEC 61111.

501
00:29:21,967 --> 00:29:26,467
Then the systemic work, one to three
months, with the Project Management Team in the

502
00:29:26,507 --> 00:29:26,747
lead.

503
00:29:27,727 --> 00:29:32,267
Re run all nine QA/QC hold points with
genuine, witnessed inspection.

504
00:29:33,027 --> 00:29:38,887
Mandate a minimum PMT and EPC presence on
site and institute a permit audit regime.

505
00:29:39,867 --> 00:29:43,167
Reset the commissioning safety culture and
cap working hours.

506
00:29:44,155 --> 00:29:45,895
Notice who leads that last one.

507
00:29:46,235 --> 00:29:48,894
The people with the offices a hundred
metres away.

508
00:29:49,435 --> 00:29:49,735
Yes.

509
00:29:50,135 --> 00:29:54,015
The people who stamped the cover sheet are
the ones asked to repair the system that

510
00:29:54,075 --> 00:29:54,435
let them.

511
00:29:55,135 --> 00:29:56,155
I think that's deliberate.

512
00:29:56,815 --> 00:30:01,755
The report's closing statement says a
single working control at any layer would most

513
00:30:01,795 --> 00:30:03,575
likely have prevented this fatality.

514
00:30:04,235 --> 00:30:09,655
A compliant panel, one genuine QA/QC
inspection, a valid electrical permit,

515
00:30:10,075 --> 00:30:13,775
proper supervision, the correct tools, or
arc rated PPE.

516
00:30:14,575 --> 00:30:19,275
And the duty now, in his words, is to
ensure that no future task is allowed to

517
00:30:19,295 --> 00:30:22,515
proceed with every defence simultaneously
down.

518
00:30:23,265 --> 00:30:24,505
Ten minutes, he said.

519
00:30:25,185 --> 00:30:29,625
It could have been a perfectly ordinary
ten minutes, if any one of those things had

520
00:30:29,645 --> 00:30:30,145
been real.

521
00:30:30,945 --> 00:30:32,625
That's the line I'll carry out of this
one.